Construction of Upper Thulokhola Hydropower Completed ; Test Production Begins
Summary
The 22.5 MW Upper Thulokhola Hydropower Project in Myagdi has completed construction and begun test production, with electricity to be linked to the central grid.
Key Points
- The 22.5 MW Upper Thulokhola Hydropower Project in Myagdi has finished construction and started test production.
- The project is run-of-river type with infrastructure including a dam, pipelines, powerhouse, and a 5 km 132 KV transmission line from Phedi to Bandi.
- Electricity generated will connect through Dana Khurkot Transmission Line in collaboration with nearby hydropower projects.
- The project's estimated cost is Rs 3 billion, funded mainly through bank loans, promoter investment, and public IPO shares.