Marsyangdi Hydropower Center Resumes Power Generation After Completion of Major Maintenance

Summary

The 69 MW Marsyangdi Hydropower Center in Tanahun has resumed power generation after completing major maintenance and technical upgrades following a 21-day shutdown.

Key Points
  • Power generation resumed at the 69 MW Marsyangdi Hydropower Center after 21 days of maintenance.
  • Maintenance included repairing the Under Sluice Gate, which was non-operational for 14 years, and removing accumulated sand in the compensating pool.
  • Civil and mechanical works were completed with minimal impact on production during low river flow.
  • Upgrades will improve production capacity and reduce technical risks at the center.