Dhading's Naubise-Nagdhunga Road Project Nears Completion, 85% Finished

Summary

Construction on the Naubise-Nagdhunga road in Dhading is 85% complete, with remaining work including blacktopping and an overhead bridge, delayed slightly by elections and local disputes.

Key Points
  • The Naubise-Nagdhunga road project in Dhading has completed 85% of its construction work.
  • Key remaining tasks include the third layer of blacktopping and an overhead bridge at Khanikhola, to be completed within 35 days.
  • Construction delays occurred due to local disputes and electric poles on the road.
  • Upcoming local elections and the Holi festival might cause slight further delays in project completion.