Nepal Electricity Authority Launches Crucial Tansen-Burtiwang 132kV Double Circuit Transmission Line

Summary

The Nepal Electricity Authority has launched the Tansen-Burtiwang 132kV double circuit transmission line, enhancing reliable electricity supply across multiple districts.

Key Points
  • The Nepal Electricity Authority (NEA) inaugurated the Tansen-Burtiwang 132kV double circuit transmission line connecting Gulmi and Baglung districts.
  • Regular electricity flow commenced after a successful two-day technical test of the transmission line.
  • NEA Executive Director Hitendra Dev Shakya inspected the substations associated with the project and highlighted its benefits for industrial growth and employment.
  • The project involved the construction of five substations from Motipur in Kapilvastu to Burtiwang in Baglung with an investment of approximately 4.76 billion rupees.