Nepal Electricity Authority Launches Crucial Tansen-Burtiwang 132kV Double Circuit Transmission Line
Summary
The Nepal Electricity Authority has launched the Tansen-Burtiwang 132kV double circuit transmission line, enhancing reliable electricity supply across multiple districts.
Key Points
- The Nepal Electricity Authority (NEA) inaugurated the Tansen-Burtiwang 132kV double circuit transmission line connecting Gulmi and Baglung districts.
- Regular electricity flow commenced after a successful two-day technical test of the transmission line.
- NEA Executive Director Hitendra Dev Shakya inspected the substations associated with the project and highlighted its benefits for industrial growth and employment.
- The project involved the construction of five substations from Motipur in Kapilvastu to Burtiwang in Baglung with an investment of approximately 4.76 billion rupees.