Electric Poles Hamper Upgrading Work on Naubise-Malekhu Road Section
Summary
Upgrading work on the Naubise-Malekhu road is delayed due to electric poles not being relocated on time by the Nepal Electricity Authority, causing construction challenges and paving issues.
Key Points
- Upgrading work on the Naubise-Malekhu road is significantly delayed due to electric poles obstructing construction.
- The Nepal Electricity Authority (NEA) has failed to relocate over 200 electric poles despite budget being provided 18 months ago.
- Blacktopping has been done over poles in certain areas, raising safety concerns about future accidents.
- The construction delay is further compounded by upcoming elections and ineffective contractor mobilization by NEA for pole relocation.