Karnali is now brighter than ever
Summary
The completion of the Kohalpur–Surkhet 132 kVA transmission line significantly boosts electricity supply in Karnali Province, increasing power availability from 17 MW to 200 MW and improving reliability for nine districts.
Key Points
- The Kohalpur–Surkhet 132 kVA transmission line has been completed, increasing Karnali Province's electricity supply from 17 MW to 200 MW.
- The project faced delays due to tree felling disputes, land acquisition issues, and the COVID-19 pandemic, finishing three and a half years late.
- The transmission line was funded by the Government of Nepal and Nepal Electricity Authority, costing Rs 1.45 billion in total.
- Plans are underway to extend the transmission line from Surkhet to Dailekh and eventually to Jumla to further improve electricity access.