Kathmandu-Terai Expressway Project Faces Delays Amidst Weak Government Decision-Making
Summary
The Kathmandu-Terai Expressway project faces significant delays due to weak government decision-making and unresolved land acquisition issues, with only 45 percent physical progress after eight and a half years, leading to increased costs and extended deadlines.
Key Points
- The Kathmandu-Terai Expressway project has only reached 45.15 percent physical progress after eight and a half years, far behind schedule.
- Land acquisition disputes, especially in the Khokana-Dukuchhap section, have halted progress and delayed construction procurement processes.
- The project's cost has increased by 20.95 percent to NPR 211.93 billion due to delays and deadline extensions.
- Out of 7 planned tunnels, some have achieved excavation breakthroughs while others have minimal progress; bridge and road construction are ongoing but incomplete.